In relation to Land Transport Authority’s extension to the Thomson East Coast Line, Utilities such as Sewer, Water, Power Cables, Telcos are required to be diverted out of the Station Footprint.

ALPC was awarded the Main Contractor under T3002 as an Advance Sewer & Water Diversion Works to facilitate Tanjong Rhu & Katong Park Station. Besides that, there is also a requirement to construct a Common Utility Trench to divert the utilities out of future Tanjong Rhu Station.

In addition, ALPC is also required to facilitate the utilities diversion works at 3 more station, Katong Park Station, Tanjong Katong Station & Marine Parade Station.

The contract value for T3002 is up to S$44.8million.